Fire Water Network at DUGAS Facility
Alucor successfully completed EPC works for removal and installation of new fire water network at DUGAS facility in Jebel Ali. The project, executed between Q3 2020 and Q1 2021, involved installation of 5.5km GRP pipeline as well as fire prevention equipment.
​
One of the most notable aspects of this endeavor was the execution of all installation works within the challenging context of brownfield conditions, where the facility remained operational throughout the project duration.
This achievement highlights ALUCOR's unparalleled expertise in managing complex projects in live plant environments, ensuring minimal disruptions while delivering crucial upgrades to enhance safety and operational efficiency at the DUGAS facility.
​
Despite all challenges, our team completed the project ahead of schedule while maintaining the highest standards of safety and quality.
​
The ALUCOR team is proud of this accomplishment and we look forward to continue working on such challenging projects in the future.